  • Neftaly Daily Performance Report Progress Review meeting report 04 January 2026

    Neftaly Daily Performance Report Progress Review meeting report 04 January 2026

    1. Purpose of the Meeting

    The purpose of the meeting was to review progress on daily performance reports, assess current performance levels, and identify areas requiring management intervention.


    2. Opening

    The meeting was formally opened with a song led by Ms Ditsoabane, followed by a prayer led by Mr Makano.


    3. Attendance

    Present:

    Apology:

    The apology was noted and accepted.


    4. Key Matters Discussed

    4.1 Request to Review SCDR Reports Daily

    The Development Manager formally requested permission to review SCDR reports on a daily basis. The rationale for this request included:


    4.2 Low Performance on Awareness Activities

    The meeting noted low performance in awareness initiatives, which raised the following concerns:

    The team acknowledged that this area requires urgent attention and improvement in strategy, execution, and outreach efforts.


    5. Observations

    From the discussions, the following general observations were made:

  • Neftaly Daily Performance Report Progress Review meeting 04 January 2026

    Neftaly Daily Performance Report Progress Review meeting 04 January 2026

    1. Opening

    The meeting commenced with a song led by Ms Ditsoabane, followed by a prayer led by Mr Makano.


    2. Attendance

    Present:

    • Mr Makano
    • Ms Ditsoabane
    • Ms Ralepelle
    • Ms Shihangu

    Apology:

    • Mr Macuacua

    The apology was noted and accepted.


    3. Matters Discussed

    3.1 Review of SCDR Reports

    • The Development Manager requested formal permission to review SCDR reports on a daily basis.
    • The purpose of the daily review would be to:
      • Monitor progress more closely,
      • Identify performance gaps early, and
      • Provide timely feedback reports to management.

    3.2 Low Performance on Awareness Activities

    • The meeting noted low performance in awareness initiatives.
    • Concerns were raised that limited awareness could negatively affect the enrolment according to the implementation.
  • NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 04 February 2026 NeftalyPD409D5

    NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 04 February 2026 NeftalyPD409D5

    To the CEO of Neftaly, Neftaly Malatjie, Royal Committee Chairperson Clifford Legodi, Neftaly Royal Chiefs and Human Capital

    Kgotso ebe le lena

    Neftaly Daily Activity Report
    NeftalyCode: NeftalyCDR
    Position: Neftaly Development Volunteer
    Internship/Learnership: Neftaly Development Specialist
    Full Name: Daniel Makano
    Date: 04 February 2026
     
    In Partnership With: Neftaly
     
    SETA/Funder: Neftaly
     
    University/College: Varsity College
     
    1: Overview of the Day’s Activities

    • None

    2: Key Tasks Completed

    Completed Tasks

    Task 1: Uploading Documents

    • https://southernafricayouth-my.sharepoint.com/:f:/g/personal/saypro-executive_southernafricayouth_org/IgD31xLvrpGkTqbKWi0C2Xh_AfqOFeR3u-YQ8_ne9fEgrWg?e=9PJKiq
    • https://southernafricayouth-my.sharepoint.com/:f:/g/personal/saypro-executive_southernafricayouth_org/IgCO-ObrfODQRJfSbTrmDARRATN6H7AFsOmwXxwaWEBhm_Y?e=9YLfPs
    • https://southernafricayouth-my.sharepoint.com/:f:/g/personal/saypro-executive_southernafricayouth_org/IgCPtJ0SMfP7RatjIrzs_kBUAUeLrYS5Zv65eo5sjXA0HeU?e=WphyEr
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQDJJ8jkE78-TrQv-Eclr95QAd3qDsq-hEULp0Qw2Tar6KM?e=KT8Z9V
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQC-omIzAF1aTq83NNcv-FMMAQs1RYXRRyrwil7b1UlsYVs?e=bLkAin
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQDA_mxjJPDaSYvGXpta1Z6gAV-sZVUXt4pstBhhQkaklNY?e=j4p3vt
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQDsRixKM1fySYtL39DR6sg2AWBefnZyT5o85_wb-DvNa_s?e=3cLrS1
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQCSg_vR6qumRLqXrsIgub-6AS9KsOUurUOxJDP-nKhM0oQ?e=kd6vqC

    Task 2: Neftaly provided Advice & Referral to 20 people on 04 February 2026 in partnership with Accenture – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-advice-referral-to-20-people-on-04-february-2026-in-partnership-with-accenture-saypro-daily-reporting/

    Task 3: Neftaly provided Youth Mobilization to 08 people on 04 February 2026 in partnership with the Gauteng Department of Social Development – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-youth-mobilization-to-08-people-on-04-february-2026-in-partnership-with-the-gauteng-department-of-social-development-saypro-daily-reporting/

    Task 4: Neftaly provided Life Skills to 08 people on 04 February 2026 in partnership with the Gauteng Department of Social Development – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-life-skills-to-08-people-on-04-february-2026-in-partnership-with-the-gauteng-department-of-social-development-saypro-daily-reporting/

    4: Challenges Encountered :
     
    Challenge 1: Computer
    Challenge 2: Access on Other Website
    Challenge 3: Network issue

    5: Support/Assistance Required :

    • None

    6: Reflection and Personal Growth
     
    I now know how to plush events , i have learned how to work as a team and personally still learning from others:
     
    7: Goals for tomorrow
    Set your objectives or tasks to focus on for the next working day:
     
    Goal 1 – Check on daily Basis

    Signature:
    Intern/Learner Name & Surname:
    Supervisor Name & Signature (if applicable):

    My message shall end here

    Daniel Makano | Neftaly Development Specialist | Neftaly

  • NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 03 February 2026 NeftalyPD409D5

    NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 03 February 2026 NeftalyPD409D5

    To the CEO of Neftaly, Neftaly Malatjie, Royal Committee Chairperson Clifford Legodi, Neftaly Royal Chiefs and Human Capital

    Kgotso ebe le lena

    Neftaly Daily Activity Report
    NeftalyCode: NeftalyCDR
    Position: Neftaly Development Volunteer
    Internship/Learnership: Neftaly Development Specialist
    Full Name: Daniel Makano
    Date: 03 February 2026
     
    In Partnership With: Neftaly
     
    SETA/Funder: Neftaly
     
    University/College: Varsity College
     
    1: Overview of the Day’s Activities

    • None

    2: Key Tasks Completed

    Completed Tasks

    Task 1: Uploading Documents

    • https://southernafricayouth-my.sharepoint.com/:f:/g/personal/saypro-executive_southernafricayouth_org/IgDFV4_x5e2SQ5y0oqPc43EjAdRGFTrpBxITKHxeKpZ6JnU?e=x3pS6W
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQDT7ksSsuFyTa__b232c1pQAQcBUw6Yt8Aqt0X__voo9_c?e=NBFcKO
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQCHJPe2I958RZNY3TN-NefJARuwBUdMEYA5AolVOogsGZo?e=E3yCx4

    Task 2: Neftaly provided Advice & Referral to 02 people on 03 February 2026 in partnership with Accenture – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-advice-referral-to-02-people-on-03-february-2026-in-partnership-with-accenture-saypro-daily-reporting/

    Task 3: NeftalyCDR: HEALTH & SAFETY REPORT

    • https://ideas.neftaly.net/sayprocdr-health-safety-report-2/

    Task 4: Neftaly provided Life Skills to 08 people on 03 February 2026 in partnership with the Gauteng Department of Social Development – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-life-skills-to-08-people-on-03-february-2026-in-partnership-with-the-gauteng-department-of-social-development-saypro-daily-reporting/

    4: Challenges Encountered :
     
    Challenge 1: Computer
    Challenge 2: Access on Other Website
    Challenge 3: Network issue

    5: Support/Assistance Required :

    • None

    6: Reflection and Personal Growth
     
    I now know how to plush events , i have learned how to work as a team and personally still learning from others:
     
    7: Goals for tomorrow
    Set your objectives or tasks to focus on for the next working day:
     
    Goal 1 – Check on daily Basis

    Signature:
    Intern/Learner Name & Surname:
    Supervisor Name & Signature (if applicable):

    My message shall end here

    Daniel Makano | Neftaly Development Specialist | Neftaly

  • NeftalyP409-8-1-4 Neftaly Chief Develepmenment Officer SCDR Daily Chief Andrice Macuacua on 02 February 2026 NeftalyPD409D5

    NeftalyP409-8-1-4 Neftaly Chief Develepmenment Officer SCDR Daily Chief Andrice Macuacua on 02 February 2026 NeftalyPD409D5

    To the CEO of Neftaly, Neftaly Malatjie, Royal Committee Chairperson Clifford Legodi, Neftaly Royal Chiefs and Human Capital

    Kgotso ebe le lena

    Neftaly Daily Activity Report
    NeftalyCode: NeftalyCDR
    Position: Neftaly Development Officer
    Internship/Learnership: System Development
    Full Name: Andrice Macuacua
    Date: 02 February 2026

    In Partnership With: Neftaly

    SETA/Funder: Neftaly

    University/College: None

    1: Overview of the Day‘s Activities

    Completed Task

    Attended development Meeting

    1. NeftalyCDR – daily day planning meeting Minutes 02 February 2026
      -https://ideas.neftaly.net/idea/sayprocdr-daily-day-planning-meeting-minutes-02-february-2026/
    2. NeftalyCDR – Daily Review Meeting Minutes 02 February 2026
      -https://ideas.neftaly.net/idea/sayprocdr-daily-review-meeting-minutes-02-february-2026/
    3. NeftalyCDR – Daily today Events Report Review Minutes
    • https://ideas.neftaly.net/idea/sayprocdr-daily-today-events-report-review-minutes/

    4.NeftalyCDR – Daily Challenge Meeting minutes 02 February 2026
    -https://ideas.neftaly.net/idea/sayprocdr-daily-challenge-meeting-minutes-02-february-2026/

    1. NeftalyCDR – daily Feedback Report meeting munutes 02 February 2026
      -https://ideas.neftaly.net/idea/sayprocdr-daily-feedback-report-meeting-munutes-02-february-2026/

    Task 2

    created Report
    NeftalyCDR – daily day planning meeting Report 02 February 2026
    -https://ideas.neftaly.net/idea/sayprocdr-daily-day-planning-meeting-report-02-february-2026/

    NeftalyCDR Daily Review Meeting Report 02 February 2026
    -https://ideas.neftaly.net/idea/sayprocdr-daily-review-meeting-report-02-february-2026/

    NeftalyCDR – Daily today Events Report Review Report
    -https://ideas.neftaly.net/idea/sayprocdr-daily-today-events-report-review-report/

    Neftaly Daily Challenge Meeting Report 02 February 2026
    -https://ideas.neftaly.net/idea/saypro-daily-challenge-meeting-report-02-february-2026/

    NeftalyCDR – DAILY FEEDBACK MEETING REPORT
    -https://ideas.neftaly.net/idea/sayprocdr-daily-feedback-meeting-report/

    Did Daily videos

    : Challenges Encountered :

    Challenge 1: Computer
    Challenge 2: NeftalyCDR need Camera for Daily Videos
    Challenge 3: Access on Other Website
    Challenge 4: Network issue
    Challenge 5: issue of Water shortage Made us not to work well Monday

    5: Support/Assistance Required :

    None
    6: Reflection and Personal Growth

    team and personally still learning from others:

    7: Goals for tomorrow
    Set your objectives or tasks to focus on for the next working day:

    Goal 1 – Check on daily Basis

    Signature:
    Intern/Learner Name & Surname:
    Supervisor Name & Signature (if applicable):

    My message shall end here

    Andrice Macuacua| Neftaly Development Officer | Neftaly

  • Neftaly Daily Challenge Meeting Report 02 February 2026

    Neftaly Daily Challenge Meeting Report 02 February 2026

    Meeting Type: Daily Challenge Meeting Report
    Minutes Taken By: Andrice Macuacua
    Date: 02 February 2026
    Venue: Diepsloot Youth Project (DYP) Center


    Table of Contents

    1. Attendance
    2. Opening
    3. Purpose of the Meeting
    4. Discussion Points
    5. Resolutions and Action Points
    6. Closing

    1. Attendance

    Present:

    Apologies: None


    2. Opening

    The meeting commenced with an opening song led by Ntshuxeko Shihangu, followed by a prayer delivered by Daniel Makano. The session was formally initiated thereafter, setting the stage for constructive engagement on operational challenges.


    3. Purpose of the Meeting

    The purpose of the meeting was to discuss current operational challenges affecting Neftaly Development activities and to agree on practical solutions that will support efficiency, accountability, and continuity of work.


    4. Discussion Points

    4.1 Website Accessibility
    Websites critical to Neftaly operations are currently inaccessible due to technical issues. This has significantly impacted communication, reporting, and access to essential information.

    4.2 Daily Report Handover Challenges
    The team reported difficulty in handing over daily reports from the Chief, as the position is currently vacant. This gap is causing delays in reporting and disrupting workflow continuity.

    4.3 Water Supply Issue
    A lack of water supply at the premises was reported. Team members requested permission to leave early on a daily basis until the issue is resolved, citing health and operational concerns.

    4.4 Childcare Concerns
    It was noted that some staff members are facing childcare challenges, which may be affecting attendance and productivity. The importance of ensuring adequate childcare arrangements was emphasized.

    4.5 SCDR Members’ Absence Without Notice
    Some SCDR members have reportedly left work without notifying supervisors, allegedly due to frustration over unpaid salaries. This behavior negatively affects team cohesion and project delivery.

    4.6 Internet/WiFi Connectivity Issues
    Intermittent or unavailable WiFi and internet access continue to hamper productivity and limit the team’s ability to perform essential tasks.

    4.7 Computer Security and Usage
    Concerns were raised about staff changing PC passwords and PINs without authorization. It was reiterated that computers are company property and should not be used for personal purposes or modified without proper approval.


    5. Resolutions and Action Points

    IssueActionResponsible Person/Team
    Website inaccessibilityReport the issue to IT support and conduct follow-upsAssigned IT Personnel
    Daily report handover gapIdentify an interim reporting process until the Chief position is filledManagement Team
    Water supplyContact building management or plumbing services to restore waterFacilities Team
    Childcare concernsEncourage staff to arrange adequate childcare solutionsHR Department
    SCDR member absenteeismAddress salary payment delays and improve communicationFinance & HR
    Internet connectivityInvestigate and improve WiFi reliabilityIT Team
    Computer securityEnforce IT policies regarding PC access and password managementIT & Administration

    6. Closing

    The meeting concluded with a shared commitment to address the highlighted challenges as a matter of urgency. Team members agreed to collaborate closely to ensure smoother operations and maintain productivity within Neftaly Development.

  • Neftaly Chief Development Officer Monitoring and Evaluation (M&E) Plan January – March 2026 (Q4)

    Neftaly Chief Development Officer Monitoring and Evaluation (M&E) Plan January – March 2026 (Q4)


    To the CEO of Neftaly Mr. Neftaly Malatjie, the Chairperson Mr. Legodi, Neftaly Royal Committee Members and all Neftaly Chiefs and Neftaly Human capital

    Kgotso a ebe le lena

    TABLE OF CONTENTS

    Neftaly Chief Development Officer Monitoring and Evaluation (M&E) Plan
    Implementation Period: January 2026 – March 2026 (Q4)

    1. INTRODUCTION
    2. 1.1 Background and Context of the Q4 M&E Plan

    Neftaly implements a range of development programmes aimed at empowering youth, women, and persons with disabilities through education, skills development, and community-based initiatives. To ensure these programmes are delivered effectively and achieve their intended outcomes, a structured Monitoring and Evaluation (M&E) system is required. This Q4 M&E Plan provides a clear framework for monitoring programme performance and evaluating results during the period January to March 2026.

    1.2 Purpose of the Monitoring and Evaluation Plan

    The purpose of this M&E Plan is to guide the systematic monitoring of programme activities, measure performance against agreed targets, and assess the impact of Neftaly’s interventions. The plan supports evidence-based decision-making, accountability, and continuous improvement.

    1.3 Objectives of the Q4 (January–March 2026) M&E Plan

    The objectives of the Q4 M&E Plan are to:

    Track progress against programme plans and targets

    Measure performance using agreed Key Performance Indicators (KPIs)

    Assess beneficiary reach and programme impact

    Identify challenges, risks, and areas for improvement

    Inform management decisions and corrective actions

    1.4 Scope of the Plan

    This plan applies to all Neftaly programmes, projects, and functional areas implemented during Q4 (January–March 2026). It covers monitoring of activities, outputs, outcomes, and reporting across all development initiatives under the oversight of the Chief Development Officer.

    1.5 Intended Users of the M&E Plan

    The M&E Plan is intended for use by Neftaly management, executive leadership, the Board, programme managers, and relevant stakeholders, including donors and partners where applicable.

    1.6 Alignment with Neftaly Strategic Plan, QIP 2026, and Internal Policies

    This plan is aligned with the Neftaly Strategic Plan, the 2026 Quality Implementation Plan (QIP), and all relevant internal policies and reporting requirements. It ensures consistency between planning, implementation, monitoring, and reporting.

    1. ORGANISATIONAL, PROGRAMME, AND OPERATIONAL CONTEXT
      2.1 Neftaly Mandate and Development Focus Areas

    Neftaly’s mandate is to empower communities by improving access to education, skills development, entrepreneurship, and social support services. The organisation focuses on inclusive development, with specific attention to youth, women, and persons with disabilities.

    2.2 Overview of Q4 (Jan–Mar 2026) Programmes and Targets

    During Q4, Neftaly will implement approved programmes in line with the Annual Implementation Plan. Each programme has defined outputs, beneficiary targets, and performance indicators that will be monitored throughout the quarter.

    2.3 Strategic Priorities for the Quarter

    Key priorities for Q4 include effective programme delivery, achievement of quarterly targets, quality service provision, and preparation for year-end reporting and planning.

    2.4 Role and Accountability of the Chief Development Officer

    The Neftaly Chief Development Officer is responsible for overall oversight of programme performance and M&E implementation. The Neftaly Chief Development Officer ensures that monitoring systems are functional, performance is reviewed regularly, and corrective actions are implemented where required.

    2.5 Relationship Between the Neftaly Chief Development Officer, Programme Managers, and M&E Functions

    Programme Managers are responsible for collecting and submitting performance data, while M&E support functions provide tools, guidance, and quality assurance. The Neftaly Chief Development Officer coordinates these roles and ensures alignment across all programmes.

    2.6 Governance, Oversight, and Reporting Structures

    M&E reporting flows from programme level to management and executive oversight structures. Quarterly reports are reviewed and approved through established governance processes.

    1. MONITORING AND EVALUATION APPROACH
      3.1 Definition and Purpose of Monitoring

    Monitoring is the continuous tracking of programme activities and outputs to ensure implementation is progressing as planned.

    3.2 Definition and Purpose of Evaluation

    Evaluation focuses on assessing the effectiveness, relevance, and impact of programmes in achieving intended outcomes.

    3.3 Results-Based Management (RBM) Framework

    Neftaly applies a Results-Based Management approach to link activities to outputs, outcomes, and long-term impact.

    3.4 Logical Framework

    The logical framework outlines inputs, activities, outputs, outcomes, and impact for each programme and guides performance measurement.

    3.5 Integration of M&E into Operations

    Monitoring activities are integrated into daily, weekly, and monthly operations to ensure timely data collection and reporting.

    3.6 Alignment with NeftalyCDR Reporting Timelines

    All M&E activities align with NeftalyCDR reporting schedules to ensure consistency and compliance.

    1. PERFORMANCE MANAGEMENT AND KPI FRAMEWORK
      4.1 Overview of Neftaly Performance Management System

    The performance management system tracks progress against agreed KPIs and targets.

    4.2 KPI Development, Approval, and Review

    KPIs are developed during planning, approved by management, and reviewed quarterly.

    4.3 KPI Categories

    KPIs include programme delivery, beneficiary reach and inclusion, quality and impact, and financial efficiency indicators.

    4.4 KPI Tracking per Programme

    Each programme tracks KPIs monthly and consolidates results quarterly.

    4.5 Baselines and Targets

    Baselines, monthly targets, and quarterly targets are clearly defined for accurate performance measurement.

    4.6 Data Sources and Verification

    Data is collected using standard tools and verified to ensure accuracy and reliability.

    4.7 Performance Rating System

    Performance is assessed using a scoring and traffic-light system to highlight progress and risks.

    1. QUARTERLY PERFORMANCE REVIEWS

    Quarterly performance reviews assess overall programme performance against KPIs, identify challenges, and agree on corrective actions. Reviews include preparation of documentation, performance analysis, management decisions, and follow-up on action items.

    1. BENEFICIARY IMPACT ASSESSMENTS

    Beneficiary impact assessments measure how programmes have improved skills, economic opportunities, and social outcomes. Data is disaggregated by youth, women, and persons with disabilities, and findings are used to improve programme design and delivery.

    1. DATA COLLECTION, MANAGEMENT, AND QUALITY ASSURANCE

    Clear roles and standard tools are used for data collection. Data quality is ensured through validation, secure storage, confidentiality measures, and compliance with ethical and data protection standards.

    1. QUARTERLY PERFORMANCE REPORT (JANUARY–MARCH 2026)

    The quarterly performance report presents consolidated programme results, KPI achievement, beneficiary impact, challenges, risks, and recommendations. Reports are reviewed, approved, and shared with relevant stakeholders within agreed timelines.

    1. LEARNING, ADAPTATION, AND CONTINUOUS IMPROVEMENT

    M&E findings are used to identify lessons learned, best practices, and areas for improvement. Feedback informs programme adjustments and future planning.

    1. RISK MANAGEMENT IN M&E

    Potential operational, data, and reporting risks are identified and mitigated through ongoing monitoring and corrective actions.

    1. ROLES AND RESPONSIBILITIES

    Clear roles are defined for the Chief Development Officer, programme managers, M&E support staff, senior management, and governance structures to ensure accountability and effective implementation.

    1. Q4 IMPLEMENTATION SCHEDULE AND RESOURCES

    The M&E implementation schedule outlines key activities, timelines, and resource requirements for January to March 2026 to ensure effective execution of this plan. Oversight

    Q4 IMPLEMENTATION SCHEDULE AND RESOURCES
    12.1 Detailed M&E Activity Plan (January–March 2026)

    The Monitoring and Evaluation activities for Q4 will be implemented in line with the approved programme schedules and reporting timelines. Key activities include routine data collection, monthly KPI tracking, quarterly performance reviews, beneficiary impact assessments, and the preparation of the Q4 Performance Report. Activities will be conducted on a daily, weekly, and monthly basis to ensure timely monitoring and early identification of performance gaps.

    12.2 Resource Requirements and Budget Allocation

    The implementation of the Q4 M&E Plan will utilise existing organisational resources, including programme staff, M&E tools, and reporting systems. Budget allocations will support data collection activities, monitoring visits, performance review meetings, and reporting processes. Resource utilization will be monitored to ensure cost-effectiveness and alignment with approved budgets.

    12.3 Capacity Building and Technical Support for M&E

    Capacity building will be provided to programme managers and relevant staff to strengthen data collection, reporting, and performance analysis. Technical support will focus on the correct use of M&E tools, KPI tracking, data quality assurance, and reporting standards to ensure consistent and reliable performance information.

    12.4 Monitoring the Implementation of the M&E Plan

    The Chief Development Officer will oversee the implementation of the M&E Plan throughout Q4. Progress against the M&E activities will be reviewed regularly, and any challenges identified will be addressed through corrective actions. This will ensure that the M&E Plan is implemented effectively and supports informed decision-making.

    My message shall end here

    My message shall end here
     
    Linah Ralepelle | Neftaly Chief Development Officer | Neftaly

  • NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 30 January 2026 NeftalyPD409D5

    NeftalyP409-8-1-4 Neftaly Chief Development Specialist SCDR Daily Chief Report by Daniel Makano on 30 January 2026 NeftalyPD409D5

    To the CEO of Neftaly, Neftaly Malatjie, Royal Committee Chairperson Clifford Legodi, Neftaly Royal Chiefs and Human Capital

    Kgotso ebe le lena

    Neftaly Daily Activity Report
    NeftalyCode: NeftalyCDR
    Position: Neftaly Development Volunteer
    Internship/Learnership: Neftaly Development Specialist
    Full Name: Daniel Makano
    Date: 30 January 2026
     
    In Partnership With: Neftaly
     
    SETA/Funder: Neftaly
     
    University/College: Varsity College
     
    1: Overview of the Day’s Activities

    • None

    2: Key Tasks Completed

    Completed Tasks

    Task 1: Uploading Documents

    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQChhLSRwAY2T72BFgm9_hG9AQfUDJuSVtuOpZhosdc8-1o?e=gUeSnz
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQAJbHTXhvtFQKtecnn6i5HXAVyvCeXwtDi7yc_nsHuJw94?e=aUwdWL
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQDciCiGzekaRY613MBYvaTQAYAR9i66ofW0cfkZM7YGTdc?e=nQzCMl
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQA__lut4CLHSL0sjR8e5r0QATshKvQB4A7OPF5RlBsuEC8?e=g8atYX
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQCm2vM5BiCrRawV_6uKn9q_AfRgIg2B9ZFSeEVUBCDqwEU?e=KbxmZZ
    • https://southernafricayouth-my.sharepoint.com/:b:/g/personal/saypro-executive_southernafricayouth_org/IQAvCiARv37NSaxfTU9LHw2MAStUvoTSYJ4KJyI1kXmTDQA?e=EGPfvk

    Task 2: Neftaly provided Advice & Referral to 01 people on 30 January 2026 in partnership with Accenture – Neftaly Daily Reporting

    • https://ideas.neftaly.net/saypro-provided-advice-referral-to-01-people-on-30-january-2026-in-partnership-with-accenture-saypro-daily-reporting/

    4: Challenges Encountered :
     
    Challenge 1: Computer
    Challenge 2: Access on Other Website
    Challenge 3: Network issue

    5: Support/Assistance Required :

    • None

    6: Reflection and Personal Growth
     
    I now know how to plush events , i have learned how to work as a team and personally still learning from others:
     
    7: Goals for tomorrow
    Set your objectives or tasks to focus on for the next working day:
     
    Goal 1 – Check on daily Basis

    Signature:
    Intern/Learner Name & Surname:
    Supervisor Name & Signature (if applicable):

    My message shall end here

    Daniel Makano | Neftaly Development Specialist | Neftaly

  • NeftalyP409-8-1-4 Neftaly Chief Develepmenment Specialist SCDR Daily Chief Andrice Macuacua on 29 January 2026 NeftalyPD409D5

    NeftalyP409-8-1-4 Neftaly Chief Develepmenment Specialist SCDR Daily Chief Andrice Macuacua on 29 January 2026 NeftalyPD409D5

    To the CEO of Neftaly, Neftaly Malatjie, Royal Committee Chairperson Clifford Legodi, Neftaly Royal Chiefs and Human Capital

    Kgotso ebe le lena

    Neftaly Daily Activity Report
    NeftalyCode: NeftalyCDR
    Position: Neftaly Development Specialist
    Internship/Learnership: System Development
    Full Name: Andrice Macuacua
    Date: 29 January 2026

    In Partnership With: Neftaly

    SETA/Funder: Neftaly

    University/College: None

    1: Overview of the Day‘s Activities

    Completed Tasks

    NeftalyCDR – Meeting of Upcoming Talent Show Minutes
    https://ideas.neftaly.net/sayprocdr-meeting-of-upcoming-talent-show-minutes/

    NeftalyCDR Content Creator Meeting report 28 January 2026

    • https://ideas.neftaly.net/sayprocdr-content-creator-meeting-report-28-january-2026/

    NeftalyCDR Content Creator Meeting minutes 28 January 2026

    • https://ideas.neftaly.net/sayprocdr-content-creator-meeting-minutes-28-january-2026/

    Task 2
    Daily day planning meeting
    https://ideas.neftaly.net/sayprocdr-daily-day-planning-meeting-2/

    NeftalyCDR – Daily Today Events Report Review
    https://ideas.neftaly.net/sayprocdr-daily-today-events-report-review/

    Attended development Meeting

    NeftalyCDR – Daily feedback Report Meeting
    https://ideas.neftaly.net/sayprocdr-daily-feedback-report-meeting/

    NeftalyCDR – Daily Performance Report Performance Report Progress Review Meeting
    https://ideas.neftaly.net/sayprocdr-daily-performance-report-performance-report-progress-review-meeting/

    NeftalyCDR-Daily Tomorrow Events Report Planning
    https://ideas.neftaly.net/sayprocdr-daily-tomorrow-events-report-planning/

    : Challenges Encountered :

    Challenge 1: Computer
    Challenge 2: NeftalyCDR need Camera for Daily Videos
    Challenge 3: Access on Other Website
    Challenge 4: Network issue
    Challenge 5: issue of Water shortage Made us not to work well Monday

    5: Support/Assistance Required :

    None
    6: Reflection and Personal Growth

    team and personally still learning from others:

    7: Goals for tomorrow
    Set your objectives or tasks to focus on for the next working day:

    Goal 1 – Check on daily Basis

    Signature:
    Intern/Learner Name & Surname:
    Supervisor Name & Signature (if applicable):

    My message shall end here

    Andrice Macuacua| Neftaly Development Specialist | Neftaly